Use the Gantt chart and task dependencies
See every task on a calendar, set start dates and the tasks each one waits for, and see the critical path and whether late tasks push go-live.
The Gantt chart is on the Roadmap, on every plan. Choose Gantt chart at the top of the Roadmap to switch from the phases and gates.
What it shows
- Every task as a bar from its start date to its due date, grouped by phase. A task with no start date runs from the start of its phase.
- Each phase's dates, with a diamond for its gate, and the go-live date as a dashed line.
- An arrow from each task to the tasks that wait for it.
- The critical path in amber: the chain of tasks that decides when the plan finishes. A delay to any of them moves the finish date.
- Projected slip, hatched: how far a task is expected to run past its due date, because it is late or because a task it waits for is late.
Above the chart, HRjects says whether go-live holds: the date the plan is projected to finish, and how many days before or after go-live that is.
How the projection works
- A task that is not done and is past its due date is assumed to finish today at the earliest.
- A task cannot start until every task it waits for has finished. If one runs late, the tasks after it move by the same number of days and keep their length.
- Tasks marked Done hold nothing up.
This is a projection from the dates in the plan, not a forecast. Keep task status and dates up to date for it to be useful.
Set dates and dependencies
- On the Gantt chart, click a task.
- Set its start and due dates.
- Under Waits for, tick the tasks that must finish before it can start, then press Save.
HRjects refuses a dependency that would make a loop, where a task would end up waiting for itself. When the go-live date changes, start dates move with the plan, like due dates. New projects from the HR templates start with starter tasks that already have dates and the usual dependencies, such as the first parallel payroll waiting for pay codes, the data load and the ledger export.
Filter and print
Choose Fit to width, Weeks or Months, filter by workstream, show the critical path only, or hide tasks that are done. Print or save as PDF prints the chart for a steering committee pack.
Who can do what
Everyone on a project can see the Gantt chart. Owners and Editors can change dates and dependencies.
Not available yet
Dragging bars to change dates, lags between tasks and resource levelling are not in the product today.